What's Going on with the La Pata Extension

The planned La Pata extension.
The planned La Pata extension.
From the city of San Clemente:

The contractor of La Pata Extension Project has begun the construction of the La Pata Gap Connector Phase that will extend the existing La Pata Avenue just south of Vista Montana to Calle Saluda with four new travel lanes for approximately 2.27 miles. The phase is expected to be completed in Fall 2016.

Below are the details of the project’s construction activities for the upcoming weeks: 

WHEN: May 1 to May 16, 2014, weekdays, 7 a.m. to 5:30 p.m. 

CONSTRUCTION ACTIVITIES: 

  • Clearing and Grubbing: This work involves the removal of rubbish, shrubs, trees, etc. within the construction zone to clear the way for the improvements. 
  • Refuse Removal: This work involves the excavation of refuse at the landfill. 
  • Earthwork: This work involves the excavation and relocation of existing soil. 
  • Utility Relocation: This work involves the relocation of SDG&E overhead power lines. 

WHAT TO EXPECT: 

  • Dust Mitigation: Water trucks will be on-site and used to minimize dust during working hours. 
  • Access: Access to schools, businesses, residential areas, and emergency services will be maintained at all times. 
  • Noise/Vibration: You will experience noise and vibration from back-up alarms, work crews and other related equipment during working hours. 

CLOSURES: 

  • Trail Closures: Prima Deshecha and Forster Ridgeline Trails will be closed through Fall 2016. To view map and webpage please click on this notice. 

Note: Construction activity schedules and closures are subject to change.

Boards

More »
Got a question? Something on your mind? Talk to your community, directly.
Note Article
Just a short thought to get the word out quickly about anything in your neighborhood.
Share something with your neighbors.What's on your mind?What's on your mind?Make an announcement, speak your mind, or sell somethingPost something
See more »